Project Plan
- Desk based review of existing consultations and policies
Timescale: April, May, June 2009
- Audit of existing community groups and activities
Timescale: April, May, June, July, August 2009
- Identify, engage and consult with local stakeholder groups to identify their requirements
Timescale: June, July, August, September 2009
- Review of current facilities and their state of repair
Timescale: May, June, July 2009
- Audit current youth provision and review the delivery of statutory and voluntary youth services for Polesworth. Identify needs and gaps in provision
Timescale: June, July, August 2009
- To identify key statutory and voluntary sector partners that can help with, and contribute to the project
Timescale: Duration of project
- Publicise and raise awareness of the consultation process
Timescale: duration of project
- Analyse questionnaires
Timescale: August, Sept 2009
- Prepare Strategic Sports and Leisure Needs Plan
Timescale: September 2009
- Prepare final report and recommendations
Timescale: October 2009
- Funding Trawls for newsletter, town directory, website and community building upgrades, activities, etc.
Timescale: October 2009